2017 Summer Road Program

Engineering Division

Summer 2017 Road Construction:

Pavement Overlay

Overlay maintenance consists of pavement patching, curb and gutter repairs to correct drainage deficiencies, sidewalk repair, storm sewer repairs and a new asphalt road surface.  The following areas will receive pavement overlay:

Ironwood Dr., Freeport Dr., Kingston Ln., Lockwood Dr., Aprina Ct., Schick Rd. (Ridge Ave. to Fairfield Way), Springbrook Villas Courts (which includes Neville Ct., Melbourne Ct., Karswell Ct., Farrington Ct., Darby Ct., Crandon Ct., Atherton Ct., Billings Ct., Epson Ct., Lawford Ct., Penwick Ct. & Raleigh Ct.), Springfield Dr. (Army Trail Rd. to Lake St.) and Butterfield Dr. (Army Trail Rd. to Springfield Dr.)            

This work will begin mid-May and will take approximately two and a half (2½) months to complete.  Local signage consisting of “Road Construction Ahead” signs will be posted prior to construction.

Asphalt Surface Treatment – Scrub or Fog Seal

A Scrub Seal is a light application of asphalt rejuvenator placed directly on the pavement and worked into the surface with a drag broom, with the intent of sealing the pavement and enriching the weathered and oxidized asphalt.  A Fog Seal is similar to the Scrub Seal however it does not include application with a drag broom and is utilized on newer pavements.  These surface treatments will extend the life of the pavement by slowing the deterioration of the asphalt surface.  These areas will also receive pavement patching, curb and gutter repairs to correct drainage deficiencies, sidewalk repair and pavement crack filling. The following streets will receive asphalt surface treatment:

Hillcrest Terrace, Sutherland Ln., Norton Dr., Norton Ln., Plymouth Ln., Hempstead Dr., Hempstead Ln., Royal Ln., Ivy Ln., Manor Ln., Downing Dr., Edgebrook Dr., Juniper Ln., and Hawthorne Ln.

This work will begin mid-May and will take approximately 2 ½ months to complete.  Local signage consisting of “Road Construction Ahead” signs will be posted prior to construction.

If you have any questions regarding this project you may call the Village Services Department, Engineering Division at 630-671-5676.